TARA · Intermediate · Original practice

A break in the scanning schedule

Two scanners start at 09:00 with 12 rolls of film waiting. Scanner A takes exactly 6 minutes per roll and scanner B takes exactly 9. Each scanner handles one whole roll at a time. B must be idle from 09:18 until 09:28; it may finish a roll at 09:18 and start another at 09:28. A roll cannot be interrupted or transferred. What is the earliest time by which all 12 rolls can be finished?

Choose one answer
Hint

Keep a separate record of completions for each scanner around 09:28.

Show answer and methods 2 methods

Answer

D. 09:48

Method 1 Merge two completion schedules

Starting work whenever possible makes every completion as early as possible. By 09:42, A has finished seven rolls and B has finished three, at 09:09, 09:18 and 09:37. B finishes the eleventh roll overall at 09:46. A's next completion, at 09:48, is the twelfth.

Method 2 Show an earlier finish is impossible

Strictly before 09:48, A can finish at most 7 rolls. B can finish at most 2 before its break and 2 after it, so an earlier total cannot exceed 11. At 09:48 A can have finished 8 rolls and B can have finished 4, which makes the bound attainable.